56 Procedural requirements [for section 55 orders]

56  Procedural requirements [for section 55 orders]

(1)     Before he makes a final order or confirms a provisional order, the appropriate [authority] shall give notice—

(a)     stating that [it] proposes to make or confirm the order and setting out its effect,

(b)     setting out—

(i)     the relevant condition or requirement for the purpose of securing compliance with which the order is to be made or confirmed,

(ii)     the acts or omissions which, in [its] opinion, constitute or would constitute contraventions of that condition or requirement, and

(iii)     the other facts which, in [its] opinion, justify the making or confirmation of the order, and

(c)     specifying the period (not being less than [21] days from the date of publication of the notice) within which representations or objections with respect to the proposed order or proposed confirmation may be made,

and shall consider any representations or objections which are duly made and not withdrawn.