83 Urgent works relating to Crown land

83  Urgent works relating to Crown land

(1)     After section 82A of the listed buildings Act (inserted by section 79(2)) there is inserted the following section—

“82B Urgent works relating to Crown land: application

(1)     This section applies to any works proposed to be executed in connection with any building which is on Crown land if the appropriate authority certifies—

(a)     that the works are of national importance, and

(b)     that it is necessary that the works are carried out as a matter of urgency.

(2)     The appropriate authority may, instead of making an application for consent to the local planning authority in accordance with this