51 Duration of permission and consent

51  Duration of permission and consent

(1)     Section 91 of the principal Act (limit on duration of planning permission) is amended as follows—

(a)     . . .

(b)     after subsection (3) there are inserted the following subsections—

“(3A)     Subsection (3B) applies if any proceedings are begun to challenge the validity of a grant of planning permission or of a deemed grant of planning permission.

(3B)     The period before the end of which the development to which the planning permission relates is required to be begun in pursuance of subsection (1) or (3) must be taken to be extended by one year.

(3C)