170 Execution of works required by notice of unauthorised development

170  Execution of works required by notice of unauthorised development

(1)     If any of the steps specified in a notice of unauthorised development have not been taken before the end of the period for compliance with the notice, the relevant local planning authority may—

(a)     enter the land on which the development has been carried out and take those steps, and

(b)     recover from the person who is then the owner of the land any expenses reasonably incurred by it in doing so.

(2)     Where a notice of unauthorised development has been served in respect of development—

(a)     any expenses incurred